Pipeline Project’s List
Northern Lights 2025 Expansion
Gas Company: Northern Natural Gas
Lake Mills to Albert Lea E Line – 3 miles of 36″ in Freeborn Co., MN
Elk River 3rd Branch Line – 2.43 miles of 30″ in Washington Co., MN
Farmington to Hugo C-Line – 1.91 miles of 30″ in Washington Co., MN
Tomah Branch Line Loop – 1.28 miles of 8″ in Monroe Co., MN
Construction Start Date:
April & May 2025
Contractors:
Lake Mills to Albert Lea E Line – K & K, Inc.
Elk River to 3rd Branch Line – Otis Minnesota Services, LLC
Farmington to Hugo C-Line – Otis Minnesota Services, LLC
Tomah Branch Line Loop – K & K, Inc.
FERC Docket CP24-60
CP Express Pipeline
Gas Company: Venture Global
87.5 miles of 48″ & 5.5 miles of 24″ (lateral)
Jasper Co., TX to Cameron Parish, LA
Construction Start Date: Q2 2025
Contractor:
Spread 1 – Troy Construction
Spread 2 – Sunland Construction
FERC Docket CP22-21
Midkiff Project
Gas Company: WhiteWater Midstream
81 miles of 42″
Ector Co., TX
Construction Start Date: September 15, 2025
Contractor:
Pumpco, Inc.
Ridgeline Expansion Project
Gas Company: Enbridge
114 miles of 30″ & 8 miles of 24″ lateral
Trousdale County to Roane County, TN
Construction Start Date: Fall 2025
Contractor:
Michels Pipeline
FERC Docket CP23-516
Bay Runner Pipeline
Gas Company: White Water Midstream
220 miles of 42″
Corpus Christi to Brownsville, TX
Construction Start Date: October 2025
Contractor:
Pumpco, Inc.
Hugh Brinson Pipeline
Gas Company: Energy Transfer
400 miles of 42″
42 miles of 36″ Lateral
Waha to Maypearl, TX
Construction Start Date: Q4 2025
Contractor:
Spread 1 & 2 – Troy Construction
Spread 3 – Pumpco, Inc.
Spread 4 & 5 – Prescision Pipeline
BANGL OTB Project
Gas Company: WhiteWater Midstream
140 miles of 20″
Ector & Reeves Co.’s, TX
Construction Start Date: Q4 2025
Contractor:
Pumpco, Inc.
Pelican Pipeline
Gas Company: WhiteWater Midstream
170 miles of 42″
Shreveport to Lake Charles, LA
Construction Start Date: Late 2025
Contractors:
Pumpco, Inc.
Blackcomb Pipeline
Gas Company: WhiteWater Midstream
365 miles of 42″
Permian Basin to Aqua Dulce, TX
Construction Start Date: Late 2025
Contractors:
MPG Pipeline Contractors
Pumpco, Inc.
NCHP Replacement Project
Gas Company: Columbia Gas of Ohio
9 miles of 20″
Franklin Co., OH
Construction Start Date: January 2026
Contractor:
NPL Great Lakes, LLC
Trident Intrastate Pipeline
Gas Company: Kinder Morgan
217 miles of 42″ & 33 miles of 48″
Katy, TX to Grimes, San Jacinto, Liberty, Hardin, & Jefferson Co.’s, TX
Construction Start Date: February 2026
Contractor:
Spreads 1 & 2 – Troy Construction
Spread 3 – WHC Energy Services
Bullitt County Pipeline
Gas Company: Louisville Gas & Electric
2.2 miles of 8″
Washington, KY
Construction Start Date: February 2026
Contractor:
Miller Pipeline, LLC
Southeast Supply Enhancement Project
Gas Company: Williams Transco
Eden Loop – 30.6 miles of 42″ in Pittsylvania Co., VA & Rockingham Co., NC
Salem Loop – 24 miles of 42″ in Guilford, Forsyth, & Davidson Co.’s, NC
Construction Start Date: March 2026
Contractors:
Associated Pipe Line Contractors
FERC Docket CP25-10
MVP Southgate Project
Gas Company: Mountain Valley Pipeline, LLC
31.3 miles of 30″
Pittsylvania Co., VA to Rockingham Co.’s, NC
Construction Start Date: March 2026
Contractor:
Precision Pipeline, LLC
FERC Docket CP19-14
FERC Docket CP25-60
LN-24 Pipeline Project
Gas Company: Eastern Gas Transmission & Storage
3.82 miles of 20″
Allegany & Wyoming Co.’s, NY
Construction Start Date: March 2026
Contractor:
Schmid Pipeline Construction, Inc.
FERC Docket CP26-69
Montgomery County Project
Gas Company: Centerpoint Energy
6 miles of 20″ take-up and relay
Montgomery Co., OH
Construction Start Date: March 2026
Contractor:
Otis Minnesota Services
Marcellus Project
Gas Company: EQT Midstream
6.6 miles of 30″
Marshall Co., WV and Belmont & Monroe Co.’s, OH
Construction Start Date: March 2026
Contractor:
Precision Infrastructure
Four Cities Metro Pipeline
Gas Company: Consumers Energy
8 miles of 24″
Oakland & MaComb Co.’s, MI
Construction Start Date: 2026 – 2029
Contractor:
To Be Determined
Keweenaw Connector Pipeline
Gas Company: Semco Energy Gas Co.
30 miles of 12″
Baraga Co., MI
Construction Start Date: Spring 2026
Contractor:
Price Gregory International
Longall Mining Panel M1 Project
Gas Company: Texas Eastern Transmission/Enbridge
Line 30 – .8 mile of 36″
Line 25 – 1.6 miles of 36″
Line 15 – 1.4 miles of 30″
Line 10 – 1.4 miles of 30″
Greene Co., PA
Construction Start Date: Spring 2026
Contractor:
Henkels & McCoy, Inc.
FERC Docket CP25-379
Outer Loop Utility
Gas Company: Howard Energy Partners
63 miles of 24″
Bexar, Comal, & Guadalupe Co.’s, TX
Construction Start Date: Spring 2026
Contractor:
MPG Pipeline Contractors
Trailblazer Lateral
Gas Company: Tallgrass Energy Partners
130 miles of 8″ & 10″
Adams to Jefferson Co.’s, NE
Construction Start Date: April 2026
Contractor:
Mears
Natural Gas Pipe Replacement Project
Gas Company: Centerpoint Energy
8.9 miles of 6″
Blackford & Delaware Co.’s, IN
Construction Start Date: April 2026
Contractor:
Miller Pipeline, LLC
Shippingport Lateral Project
Gas Company: National Fuel Gas Supply
7.26 miles of 24″
Beaver & Mercer Co.’s, PA
Construction Start Date: April 2026
Contractor:
Kirila Contractors, Inc.
FERC Docket CP25-541
MBTC Pipeline
Gas Company: OneOk & MPLX
65 miles of 20″ & 7 miles of 20″
Sweeny to Baytown, TX
Construction Start Date: April 2026
Contractor:
Holloman Corp.
Green Chile Project
Gas Company: Transwestern Pipeline Co., LLC
17.77 miles of 24″
Dona Ana Co., NM
Construction Start Date: April 2026
Contractor:
Equix, Inc.
FERC Docket CP26-80
Traverse Pipeline
Gas Company: WhiteWater Midstream
160 miles of 36″
Agua Dulce to Katy, TX
Construction Start Date: May 2026
Contractor:
MPG Pipeline Contractors
Dubuque Phase 10
Gas Company: Nicor Gas Company
15.2 miles of 24″
DeKalb & Kane Co.’s, IL
Construction Start Date: May 2026
Contractor:
Precision Infrastructure, LLC
Line 5 Re-Route
Gas Company: Enbridge
41.1 miles of 30″
Ashland & Iron Co.’s, WI
Construction Start Date: May 2026
Contractor:
Michels Pipeline
Tioga Pathway Project
Gas Company: National Fuel Gas
Line Z20 – 3.84 miles of 20″ in Potter Co., PA
Line YM59 – 19.48 miles of 20″ in Potter & Tioga Co., PA
Construction Start Date: May 20, 2026
Contractors:
Michels Pipeline, Inc.
FERC CP24-514
Line C46S 2026 Modernization Project
Gas Company: National Fuel Gas
2.86 miles of 16″
Erie Co., NY
Construction Start Date: May 2026
Contractor:
Otis Minnesota Services
FERC Docket CP26-41
Columbus Branch Line Project
Gas Company: Northern Natural Gas
7.5 miles of 8″
Colfax Co., NE
Construction Start Date: May 2026
Contractor:
Geeding Construction, Inc.
FERC Docket CP26-42
Davidson County Project
Gas Company: Spire
.32 mile of 12″
Davidson Co., TN
Construction Start Date: May 2026
Contractor:
Snelson Companies, Inc.
Hope Gas Project
Gas Company: Hope Gas
1.6 miles of 6″
Braxton & Gilmer Co.’s, WV
Construction Start Date: May 2026
Contractor:
Ace Pipeline, Inc.
LN-19 Pipeline
Gas Company: Eastern Gas Transmission
12.3 miles of 20″
Armstrong & Westmoreland Co.’s, PA
Construction Start Date: May 2026
Contractor:
Ace Pipeline
FERC Docket CP26-184
Abilene 3.0 Project
Gas Company: Energy Transfer
17 miles of 24″
Abilene, TX
Construction Start Date: May 2026
Contractor:
Equix, Inc.
Franklin County Project
Gas Company: Northeast Ohio Natural Gas
3.7 miles of 8″
Franklin Co., OH
Construction Start Date: May 2026
Contractor:
Apex Pipeline Services, Inc.
Cabell County Project
Gas Company: Union Oil & Gas
.68 mile of 24″
Cabell Co., WV
Construction Start Date: May 2026
Contractor:
Apex Pipeline Services
Switchgrass Lateral
Gas Company: Rockies Express Pipeline, LLC
7.2 miles of 36″
Weld Co., CO to Laramie Co., WY
Construction Start Date: Q2 2026
Contractor:
Precision Pipeline, LLC
FERC Docket CP26-28
Big Spring Pipeline
Gas Company: Enterprise Products
33 miles of 24″
Glasscock, Howard, & Martin Co.’s, TX
Construction Start Date: Q2 2026
Contractor:
Barrilleaux Energy Services
Linde NG Interconnection Lateral
Gas Company: Golden Triangle Storage, LLC
2 miles of 12″
Jefferson Co., TX
Construction Start Date: Q2 2026
Contractor:
Unknown
FERC Docket CP26-88
Line TXL0931 Project
Gas Company: Sabine Pipeline, LLC/OneOk
2.6 miles of 12″
Orange Co., TX
Construction Start Date: Q2 2026
Contractor:
Unknown
FERC Docket CP26-67
Castle Bluff Lateral
Gas Company: Ameren (Energy Transfer)
1.57 miles of 20″
Jefferson & St. Louis Co.’s, MO
Construction Start Date: Q2 2026
Contractor:
Unknown
FERC Docket CP26-30
Casey Creek Project
Gas Company: Columbia Gulf Transmission (TC Energy)
.51 miles of 30″
Adair Co., KY
Construction Start Date: Q2 2026
Contractor:
Unknown
FERC Docket CP26-47
Erie County Replacement Project
Gas Company: Eastern Gas Transmission
2.35 miles of 20″
Eric Co., NY
Construction Start Date: June 2026
Contractor:
Otis Minnesota Services
Wolf Creek Project
Gas Company: Rocky Mountain Gas
2.9 miles of 10″
Pitkin Co., CO
Construction Start Date: June 2026
Contractor:
Unknown
PLUSS Project
Gas Company: Gulf South Pipeline (Boardwalk)
4.55 miles of 30″ Replacement – St. Martin Parish, LA
1.06 miles of 20″ Lateral – Ascension Parish, LA
Construction Start Date: June 30, 2026
Contractor:
L.E. Bell Construction
FERC Docket CP25-54
SM102 Replacment Project
Gas Company: TC Energy
.5 mile of 36″
Boyd Co., KY
Construction Start Date: July 2026
Contractor:
Ace Pipeline, Inc.
Eaton County Project
Gas Company: Consumers Energy
1.6 miles of 12″
Eaton Co., MI
Construction Start Date: July 2026
Contractor:
Precision Infrastructure
Fairfax County Replacement Project
Gas Company: Washington Gas Light
1.57 miles of 12″ & 24″
Fairfax Co., VA
Construction Start Date: July 2026
Contractor:
Infrasource Construction, LLC
Miami Beach to Roney Project
Gas Company: Florida Power & Light
.56 mile of 24″ HDD
Miami-Dade Co., FL
Construction Start Date: July 2026
Contractor:
Laney Directional Drilling
Alliance Creek South Loop
Gas Company: MidAmerican Energy Company
5.8 miles of 20″
Washington Co., IA
Construction Start Date: July 2026
Contractor:
Michels Pipeline, Inc.
Lewis & Clark County Project
Gas Company: Northwestern Energy
3.5 miles of 16″ including 5 HDD’s
Lewis & Clark Co., MT
Construction Start Date: July 2026
Contractor:
Michels Pipeline, Inc.
Permian West Expansion Project
Gas Company: El Paso Natural Gas (Kinder Morgan)
9 miles of 30″
Hudspeth Co., TX
Construction Start Date: August 2026
Contractor:
Troy Construction
FERC Docket CP26-156
Tri-State Project
Gas Company: MPLX
8.154 miles of 20″
Washington Co., PA & Ohio Co., WV
Construction Start Date: August 2026
Contractor:
Alex E. Paris Contracting Co., Inc.
Caddo Parish Project
Gas Company: Delta Utilities
1.38 miles of 16″
Shreveport, LA
Construction Start Date: August 2026
Contractor:
Wayne Holden & Company, Inc.
Aquila Pipeline Project
Gas Company: Williams
18 miles of 24″
Utah Co., UT
Construction Start Date: August 2026
Contractor:
Holloman
Line KA West & Line SM-123 Relocation Project
Gas Company: Columbia Gas Transmission
Line KA West Replacement – .81 mile of 20″
Line SM-123 Replacement – .81 mile of 24″
Mingo Co., WV
Construction Start Date: Q3 2026
Contractor:
To Be Determined
FERC CP26-15
Lycoming & Sullivan County Project
Gas Company: Williams Field Services
5.3 miles of 10″, 12″, & 20″
Lycoming & Sullivan Co., PA
Construction Start Date: Q3 2026
Contractor:
Unknown
Clinton Town Border & Pipeline Relocation Project
Gas Company: Southern Star Central Gas Pipeline
2 miles of 16″
Douglas Co., KS
Construction Start Date: Q3 2026
Contractor:
Venables Construction
FERC Docket CP26-526
2026 Expansion Project
Gas Company: Great Basin Gas Transmission
Wadworth Segment – 2.32 miles of 20″ in Washoe Co., NV
Highway Segment – 2.35 miles of 20″ in Lyon Co., NV
Construction Start Date: Q3 2026
Contractor:
To Be Determined
FERC Docket CP25-209
Nueva Era Dos Pipeline
Gas Company: Nueva Era Dos, LLC
31 miles of 36″
.68 mile of 36″ (Border Crossing)
Zavala & Maverick Co.’s, TX
Construction Start Date: Q3 2026
Contractor:
To Be Determined
FERC Docket CP25-527 (For Border Crossing Segment)
Supply Lateral Project
Gas Company: Golden Pass LNG
.22 mile of 42″
Sabine Pass, TX
Construction Start Date: Q3 2026
Contractor:
To Be Determined
FERC Docket CP25-205
TTC Connector
Gas Company: TTC Connector, LLC
25 miles of 20″
Colorado & Wharton Co.’s, TX
Construction Start Date: Q3 2026
Contractor:
KCL Construction, LLC
FERC Docket CP25-525
Northeast Supply Enhancement Project
Gas Company: Williams Transco
Quarryville Loop – 10.2 miles of 42″ in Lancaster Co., PA
Madison Loop – 3.4 miles of 26″ in Middlesex Co., NJ
Raritan Bay Loop – .2 mile of 26″ in Middlesex Co., NJ and 23.3 miles of 26″ in Queens & Richmond Co.’s, NY
Construction Start Date: Q3 2026
Contractor:
Michels Pipeline
FERC Docket CP17-101
Ryckman Creek Lateral Loop
Gas Company: Northwest Pipeline, LLC (Williams)
6.75 miles of 12″
Uinta Co., WY
Construction Start Date: Q3 2026
Contractor:
Jomax Construction
FERC Docket CP26-18
Pelican Thrasher Lateral
Gas Company: WhiteWater Midstream
65 miles of 42″
Beauregard Parish, LA
Construction Start Date: Q3 2026
Contractor:
Pumpco, Inc.
Speedway NGL Pipeline
Gas Company: Targa
500 miles of 30″
Permian to Mont Belvieu, TX
Construction Start Date: August 2026
Contractor:
Spread 1 – Pumpco
Spread 2 – MPG Pipeline Contractors
Spread 3 – Troy Construction
Dude Lateral
Gas Company: Double E Pipeline, LLC
22.1 miles of 20″
Eddy & Lea Co.’s, NM
Construction Start Date: August 2026
Contractor:
To Be Determined
FERC Docket CP26-542
Stark County Project
Gas Company: Enbridge
1.43 miles of 20″ Dual Lay
Stark Co., OH
Construction Start Date: August 2026
Contractor:
Appalachian Pipeline Contractors
T15 Reliability Project
Gas Company: Dominion Energy
45 miles of 36″
Eden to Roxboro, NC
Construction Start Date: August 2026
Contractors:
Precision Pipeline, LLC
Buffalo Run Pipeline
Gas Company: Targa
30 miles of 36″
Glasscock, Midland, Reagan, & Upton Co.’s, TX
Construction Start Date: September 2026
Contractor:
Equix, Inc.
Botetourt County Project
Gas Company: Columbia Gas
1.32 miles of 6″
Eagle Rock, VA
Construction Start Date: September 2026
Contractor:
NPL Great Lake, LLC
South System Expansion 4 Project
Gas Company: Southern Natural Gas
18 miles of 20″, 8 miles of 24″, 74 miles of 30″, 27 miles of 36″, & 152 miles of 42″
Clarke Co., MS to Richmond Co., GA
Construction Start Date: October 2026
Contractors:
Associated Pipe Line Contractors
Rockford
Castle
FERC Docket CP25-517
South Grand Rapids Project
Gas Company: DTE Energy
3.1 miles of 24″
Grand Rapids, MI
Construction Start Date: October 2026
Contractor:
To Be Determined
Cumberland River HDD Project
Gas Company: Tennessee Gas Pipeline
.31 mile of 30″ HDD
Cheatham Co., TN
Construction Start Date: October 2026
Contractor:
To Be Determined
FERC Docket CP26-552
Delta Blues Project
Gas Company: Tennesse Gas Pipeline (Kinder Morgan)
2.35 miles of 16″
Washington Co., MS
Construction Start Date: October 2026
Contractor:
To Be Determined
FERC Docket CP26-555
McCloud Lateral Project
Gas Company: El Paso Natural Gas (Kinder Morgan)
5.8 miles of 16″
El Paso Co., TX
Construction Start Date: Q4 2026
Contractor:
To Be Determined
FERC Docket CP26-558
Harrison County Power Project
Gas Company: Natural Gas Pipeline Company of American (Kinder Morgan)
3.2 miles of 24″
Harrison Co., TX
Construction Start Date: Q4 2024
Contractor:
To Be Determined
FERC Docket CP26-565
Clarksville Lateral
Gas Company: Enable Gas Transmission (Energy Transfer)
13 miles of 16″
Pope & Johnson Co.’s, AR
Construction Start Date: Q4 2026
Contractor:
To Be Determined
FERC Docket CP26-573
Gas Company: Williams
36.9 miles of 42″
Beauregard & Calcasieu Parishes, LA
Construction Start Date: November 2026
Contractor:
To Be Determined
FERC Docket CP21-465
Line 300 Project
Gas Company: Williams
30.8 miles of 42″
Beauregard & Calcasieu Parishes, LA
Construction Start Date: November 2026
Contractor:
To Be Determined
FERC Docket CP21-465
Rochester Lateral
Gas Company: WE Energies
33 miles of 24″ & 30″
Kenosha, Milwaukee, & Racine Co.’s, WI
Construction Start Date: Late 2026
Contractor:
To Be Determined
Eiger Express Pipeline
Gas Company: WhiteWater Midstream
450 miles of 48″
Waha to Katy, TX
Construction Start Date: 2027
Contractor:
Spread 1 – Pumpco
Spread 2 – MPG Pipeline Contractors
Spread 3 – Troy Construction
One Gas Project
Gas Company: Oklahoma Natural Gas
43 miles of 24″
Fort Towson, OK
Construction Start Date: Early 2027
Contractor:
To Be Determined
Western Gateway Pipeline
Gas Company: Phillips 66 & Kinder Morgan
900 miles of 24″
Borger, TX to Phoenix, AZ
Construction Start Date: 2027
Contractors:
To Be Determined
Helena to Three Forks Natural Gas Pipeline Project
Gas Company: Northwestern Energy
74 miles of 16″
East Helena to Three Forks, MT
Construction Start Date: 2027
Contractor:
To Be Determined
Cowboy Connector
Gas Company: Enterprise Products
34 miles of 20″ & 61 miles of 24″
Ector Co., TX to Eddy Co., NM
Construction Start Date: 2027
Contractor:
To Be Determined
Corpus Christi Gas Project
Gas Company: Enbridge
18 miles of 20″
Construction Start Date: 2027
Contractors:
To Be Determined
Texas Connector
Gas Company: Texas Connector Pipeline
North Segment – 29.6 miles of 42″
South Segment – 1.4 miles of 42″
Jefferson Co., TX & Cameron Parish, LA
Construction Start Date: 2027
Contractor:
To Be Determined
FERC Docket CP18-7
FERC Docket CP23-78
FERC Docket CP24-512
Mississippi Crossing Project
Gas Company: Tennesee Gas Pipeine
178 miles of 42″ – Washington to Clarke Co.’s, MS
22 miles of 36″ – Clarke Co., MS & Choctaw Co., AL
6 miles of 36″ – Humphreys & Sunflower Co.’s, MS
Construction Start Date: January 2027
Contractors:
MPG Pipeline Contractors
FERC Docket CP25-514
Woodward Park North Columbus High Pressure System Pipeline
Gas Company: Columbia Gas of Ohio
5.3 miles of 20″
Franklin Co., OH
Construction Start Date: January 2027
Contractor:
To Be Determined
Ohio Power Siting Board Case # 25-0838-GA-BTX
Cape Cod Canal Bridge Relocation Project
Gas Company: Algonquin Gas Transmission
3.03 miles of 16″ & 2.17 miles of 18″
Cape Cod, MA
Construction Start Date: Q1 2027
Contractor:
To Be Determined
FERC Pre-Filing PF25-4
Southeast Virginia Energy Storage Project
Gas Company: Columbia Gas Transmission/TC Energy
1.02 miles of 12″
Sussex Co., VA
Construction Start Date: Q1 2027
Contractor:
To Be Determined
FERC Docket CP26-20
Constitution Pipeline
Gas Company: Williams Transco
Spread A – 47.62 miles of 30″
Spread B – 77.15 miles of 30″
Susquehanna Co., PA to Schoharie Co., NY
Construction Start Date: Q1 2027
Contractor:
To Be Determined
Appalachian Reliability Project
Gas Company: Eastern Gas Transmission
3.9 miles of 30″
Westmoreland Co., PA
Construction Start Date: Q1 2027
Contractor:
To Be Determined
FERC Docket CP25-528
Heartland Project
Gas Company: ANR Pipeline Company (TC Energy)
Wisconsin Loop Line – 48.3 miles of 36″ in Kendall, Kane, & McHenry Co.’s, IL
Southwest Loop Line – 11.3 miles of 42″ in Kendall Co., IL
Mainline 301 Replacement – 1.4 miles of 30″ in Waukesha Co., WI
Two Rivers Lateral Loop – 8.1 miles of 8″ in Sheboygan Co., WI
Construction Start Date: Q1 2027
Contractors:
To Be Determined
FERC Docket CP25-79
Big Hollow Lateral
Gas Company: Enable Mississippi River Transmission, LLC (Energy transfer)
9.5 miles of 20″
Monroe Co., IL
Construction Start Date: Q1 2027
Contractor:
To Be Determined
FERC Docket CP26-2
Alaska LNG Project
Gas Company: Alaska LNG (Conoco, Exxon, TransCanada)
800 miles of 42″
Alaska
Construction Start Date: Q1 2027
Contractors:
Precision Pipeline, LLC
Price Gregory International
JV – Michels Pipeline & ASRC Energy Services (Houston Contracting Company)
JV – Associated Pipe Line Contractors, Doyon Energy Services, & Cruz Construction
JV – Barnard Pipeline & SICIM
JV – Spiecapag (VINCI) & U.S. Pipeline
FERC Docket CP17-178
Butler County Phase 2 Natural Gas Replacement Project
Gas Company: Duke Energy
6 miles of 16″
Butler County, OH
Construction Start Date: February 2027
Contractor:
To Be Determined
Ohio Power Siting Board 22-1072-GA-BTZ
Appalachia to Market III Project
Gas Company: Texas Eastern Transmission
2 miles of 36″
Adams & York Co.’s, PA
Construction Start Date: March 2027
Contractor:
To Be Determined
FERC Docket CP25-491
Forza Pipeline
Gas Company: Targa
36 miles of 36″
Lea Co., NM to Winkler Co., TX
Construction Start Date: March 2027
Contractor:
To Be Determined
FERC Docket CP26-34
Viola Project
Gas Company: Southern Star Central Natural Gas Pipeline, Inc.
19.33 miles of 16″
Sumner Co., KS
Construction Start Date: Spring 2027
Contractors:
To Be Determined
FERC Docket CP26-74
Central Mainline Corridor Expansion Project
Gas Company: Northern Natural Gas
Omaha 3rd Branch Line Loop – 9.03 miles of 20″ in Cass & Sarpy Co.’s, NE
NPPD Princton Road Branch Line – 14.64 miles of 30″ in Gage & Lancaster Co.’s, NE
Des Moines C-Line – 2.48 miles of 20″ in Dallas Co., IA
Construction Start Date: Spring 2027
Contractor:
To Be Determined
FERC Docket CP26-241
Texas Access Project
Gas Company: Kinder Morgan Louisiana Pipeline
3.05 miles of 48″ (.99 mile of it is HDD)
Jefferson Co., TX to Cameron Parish, LA
Construction Start Date: April 2027
Contractor:
To Be Determined
FERC Docket CP26-136
Decatur Lateral Project
Gas Company: Rockies Express Pipeline (Tallgrass Energy)
16.7 miles of 20″
Macon Co., IL
Construction Start Date: April 2027
Contractor:
To Be Determined
CP25-94
Welsh Lateral Project
Gas Company: Gulf South Pipeline (Boardwalk)
16.11 miles of 16″
Titus Co., TX
Construction Start Date: April 2027
Contractor:
To Be Determined
FERC Docket CP26-557
Hubbard Lateral
Gas Company: WTG Hubbard Transmission
39.14 miles of 30″
Ellis, Hill, & Navaroo Co.’s, TX
Construction Start Date: April 2027
Contractor:
To Be determined
Critical Energy Reliability Link Project
Gas Company: Rockies Express Pipeline, Cheyenne Connector, & East Cheyenne Gas Storage
Lateral – 152.7 miles of 24″
Horizon Spur – 7 miles of 24″
Weld, Adams, Arapahoe, Elbert, & El Paso Co.’s, CO
Construction Start Date: Q2 2027
Contractor:
To Be Determined
FERC Docket CP25-539
Ventura to Farmington A-Line Replacement Project
Gas Company: Northern Natural Gas
Lake Mills M500 E-Line – 8.29 miles of 36″ in Freeborn Co., MN
Albert Lea M500 E-Line – 2.09 miles of 36″ in Steel Co., MN
Faribault M500 D-Line – 7.5 miles of 30″ in Dakota Co., MN
Construction Start Date: May 2027
Contractor:
To Be Determined
FERC Docket CP26-130
NL27 Project
Gas Company: Northern Natural Gas
Lake Mills M500 E-Line – 2.32 miles of 36″ in Freeborn Co., MN
Albert Lea M500 E-Line – 3.42 miles of 36″ in Steel Co., MN
Willmar 3rd Branch Line Upstream – 1.78 miles of 24″ in Scott Co., MN
Willmar 3rd Branch Line Downstream – 4.78 miles of 24″ in Carver Co., MN
Welcome 2nd Line – 1.24 miles of 16″ in Martin Co., MN
Paynesville 2nd Branch Line – 2.45 miles of 4″ in Stearns Co., MN
Worthington 2nd Branch Line – 2.17 miles of 8″ in Jackson Co., MN
Springfield 2nd Branch Line 7.4 miles of 8″ in Watonwan Co., MN
Minnesota Interconnect 2nd Branch Line – 1.59 miles of 12″ in Isanti Co., MN
Alexandria 2nd Branch Line – 1.28 miles of 8″ in Morrison Co., MN
Construction Start Date: May 2027
Contractor:
To Be Determined
FERC Docket CP26-130
Gabbs Lateral Relocation Project
Gas Company: Great Basin Gas Transmission
18.8 miles of 8″ & 13.8 miles of 6″
Churchill Mineral, & Nye Co.’s, NV
Construction Start Date: May 2027
Contractors:
To Be Determined
FERC Docket PF24-6
Todhunter and Yankee Road Pipe Outlet Installation Project
Gas Company: Duke Energy Ohio
.3 mile of 12″
Monroe, OH
Construction Start Date: May 2027
Contractor:
To Be Determined
Ohio Power Siting Board: 25-0008-GA-BNR
STEP Loop
Gas Company: Tennessee Gas Pipeline
1.54 miles of 30″
Nueces Co., TX
Construction Start Date: June 2027
Contractor:
To Be Determined
FERC Docket CP26-540
North System Expnasion 2 Project
Gas Company: Southern Natural Gas (Kinder Morgan)
West Loop – 3.21 miles of 24″ in Lowndes Co., MS
East Loop – 1.27 miles of 24″ in Pickens Co., AL
Construction Start Date: June 2027
Contractor:
To Be Determined
FERC Docket CP26-567
Line 5 – Great Lakes Tunnel Project
Gas Company: Enbridge
4 miles of 30″
Straits of Mackinac, MI
Construction Start Date: 2027
Contractors:
Barnard Construction
Train 4 Project
Gas Company: Freeport LNG
10.6 miles of 42″
Freeport, TX
Construction Start Date: 2027
Contractor:
To Be Determined
FERC Docket CP17-470
Saguaro Connector Pipeline
Gas Company: OneOk WesTex Transmission, LLC
155 miles of 48″
Pecos Co. to Hudspeth Co., TX
Construction Start Date: Unknown
Contractors:
To Be Determined
FERC Docket CP23-29
Permian Basin Expansion
Gas Company: Northern Natural Gas
15.1 miles of 24″ & 1.1 miles of 16″
Lea Co., NM & Gaines Co., TX
Construction Start Date: Summer 2027
Contractor:
To Be Determined
FERC Docket CP26-534
Dearborn County Lateral Project
Gas Company: Texas Gas Transmission
12 miles of 20″
Dearborn Co., IN; Boone Co., KY; and Hamilton Co., OH
Construction Start Date: Summer 2027
Contractor:
To Be Determined
FERC Docket CP26-536
Black Bayou Header Project
Gas Company: Black Bayou Storage, LLC
27.1 miles of 24″ Bi-Directional
Cameron & Calcasieu Parishes, LA
Construction Start Date: July 2027
Contractor:
To Be Determined
FERC CP24-494
Bridger Pipeline Expansion
Gas Company: Bridger Pipeline, LLC
646 miles of 36″
Phillips Co., MT to Platte Co., WY
Construction Start Date: July 2027
Contractor:
To Be Determined
Franklin Farms Project
Gas Company: ETC Tiger Pipeline, LLC (Energy Transfer)
13.24 miles of 36″ & 1.75 miles of 20″
Richland Parish, LA
Construction Start Date: July 2027
Contractor:
To Be Determined
FERC Docket CP26-549
Leidy Access Expansion Project
Gas Company: Williams Transco
3.38 miles of 42″
Luzerne Co., PA
Construction Start Date: July 2027
Contractor:
To Be determined
FERC Docket CP26-576
Texas Eastern Line 31 Expansion Project
Gas Company: Enbridge
10.2 miles of 36″ & 1.7 miles of 16″
Madison Co., MS
Construction Start Date: August 2027
Contractor:
To Be Determined
FERC Docket CP26-75
Texas Gateway Project
Gas Company: Gulf South Pipeline (Boardwalk)
155 miles of 36″ & 48″
Carthage, TX to Gillis, LA
Construction Start Date: Q3 2027
Contractor:
To Be Determined
FERC Docket CP26-547
Corpus Christi Pipeline Expansion Project
Gas Company: Cheniere Energy
26 miles of 42″
San Patricio Co., TX
Construction Start Date: Q3 2027
Contractor:
To Be Determined
FERC Pre-Filing PF25-10
Guardian 3 Expansion Project
Gas Company: Guardian Pipeline, LLC
Joliet Loop – 42.6 miles of 36″ in Kendall & DeKalb Co.’s, IL
Sycamore Loop – 25.5 miles of 36″ in DeKalb & McHenry Co.’s, IL
Construction Start Date: September 2027
Contractor:
To Be Determined
FERC Docket CP26-548
Micron Gas Main Project
Gas Company: National Grid
3 miles of 16″
Clay, NY
Construction Start Date: Fall 2027
Contractor:
To Be Determined
Mustang Express Pipeline
Gas Company: ARM Energy
Cougar Lateral – 55 miles of 42″ from Tres Palacios Storage to Katy Hub, TX
Mustang Mainline – 178 miles of 42″ from Katy to Port Arthur, TX
Golden Triangle/Spindletop Lateral – 3 miles of 42″ near Port Arthur, TX
Construction Start Date: Q4 2027
Contractors:
To Be Determined
Florida Gas Transmission, Phase IX
Gas Company: Florida Gas Transmission/Energy Transfer
95 miles of 30″ & 42″ Looping
Santa Rosa, Walton, Holmes, Liberty, Gadsen, Jefferson, Madison, Taylor, Lafayette, Union, Putnam, & Hillsboro Co.’s, FL
Green & George Co.’s, MS
Construction Start Date: Q4 2027
Contractor:
To Be Determined
Argent LNG Project
Gas Company: Argent LNG, LLC
.93 mile of 16″ dual-lay
Lafourche Parish, LA
Construction Start Date: December 2027
Contractor:
To Be Determined
FERC Pre-Filing PF25-11
2028 Expansion Project
Gas Company: Great Basin Gas Transmission
212 miles of 42″ & 36″
Humboldt to Storey Co., NV
Construction Start Date: December 2027
Contractor:
To Be Determined
FERC Pre-Filing PF26-5
Commonwealth Project
Gas Company: Commonwealth LNG, LLC
3.04 miles of 30″
Cameron Parish, LA
Construction Start Date: Delayed
Contractor:
To Be Determined
FERC Docket CP19-502
Fairview Heights Reliability Enhancement Project
Gas Company: Ameren Illinois
10 miles of 16″
Shiloh To Caseyville, IL
Construction Start Date: 2028
Contractor:
To Be Determined
Intensity Pipeline
Gas Company: Intensity Infrastructure Partners & Rainbow Energy
Phase I – 136 miles of 36″ (Watford City to Washburn, ND)
Phase II – 208 miles of 30″ (Washburn to Casselton, ND)
Construction Start Date: 2028
Contractor:
To Be Determined
Midwest Carbon Express
Gas Company: Summit Carbon Solutions
1,300 miles of up to 24″ pipe
IA, NE, & WY
Construction Start Date: 2028
Contractor:
To Be Determined
Northwoods Project
Gas Company: ANR Pipeline Company (TC Energy)
92 miles of 36″
Iron Co., MI and Florence, Marinette, Oconto, & Shawano Co.’s, WI
Construction Start Date: 2028
Contractor:
To Be Determined
FERC Docket CP26-6
Project Tundra
Gas Company: Minnkota Power Cooperative & TC Energy
5 miles of 16″
Oliver Co., ND
Construction Start Date: 2028
Contractor:
To Be Determined
Southern Illinois Connector
Gas Company: Energy Transfer & Enbridge
57 miles of 24″
Wood River to Patoka, IL
Construction Start Date: January 2028
Contractor:
To Be determined
Kosciusko Junction Pipeline Project
Gas Company: Gulf South/Boardwalk
Kosciusko Junction Pipeline – 102 miles of 36″ from Attala to Clarke Co., MS
Columbia Gulf Lateral – 8 miles of 36″ in Humphreys & Sunflower Co.’s, MS
Construction Start Date: Q1 2028
Contractor:
To Be Determined
FERC Pre-Filing PF25-6
Maysville Project
Gas Company: Columbia Gas Transmission (TC Energy)
42 miles of 30″
Rowan, Fleming, & Mason Co.’s, KY
Construction Start Date: Q1 2028
Contractor:
To Be Determined
FERC Docket CP26-25
Desert Southwest Pipeline Expansion
Gas Company: Energy Transfer
516 miles of 48″
Permian Basin, TX to Phoenix, AZ
Construction Start Date: Q1 2028
Contractor:
To Be Determined
FERC Pre-Filing PF26-9
Pulaski Project
Gas Company: TC Energy
41 miles of unknown diameter
Lincoln & Pulaski Co.’s, KY
Construction Start Date: Q1 2028
Contractor:
To Be Determined
FERC Docket CP26-11
Yuma Pipeline Project
Gas Company: LED Enterprises
140 miles of 30″
Maricopa & Yuma Co.’s, AZ
Construction Start Date: Early 2028
Contractor:
To Be Determined
FERC Pre-Filing PF25-8
NKY Gate Enhancement Project
Gas Company: TC Energy
29.2 miles of 30″ & 36″
Campbell, Pendleton, Bracken, & Nicholas Co.’s, KY
Construction Start Date: March 2028
Contractor:
To Be Determined
FERC Docket CP26-19
Phase IV Expansion Project
Gas Company: Pine Prairie Energy Center (Williams)
2.37 miles of 30″
Evangeline Parish, LA
Construction Start Date: March 2028
Contractor:
To Be Determined
FERC Docket CP25-533
Line RE Project
Gas Company: Southern Star Central Gas Pipeline
1.6 miles of 30″
Reno Co., KS
Construction Start Date: March 2028
Contractor:
To Be Determined
FERC Docket CP26-572
Line Section 32 Expansion Project
Gas Company: WBI Energy
17 miles of 24″
Williams Co., ND
Construction Start Date: Spring 2028
Contractor:
To Be Determined
FERC Docket CP26-158
North Extension Project (NEX)
Gas Company: Natural Gas Pipeline Company of America
11.5 miles of 24″
Kenosha Co., WI
Construction Start Date: Spring 2028
Contractor:
To Be Determined
FERC Docket CP26-564
Algonquin’s Reliable Affordable Resilient Enhancement Project
Gas Company: Alonquin Gas Transmission (Enbridge)
Mainline – 3 miles of 36″ in Burrillville, RI
G-1 – 8.1miles of 36″ in Franklin, MA
G-2 – 2.2 miles of 12″ in Tiverton, RI
Construction Start Date: Q2 2028
Contractor:
To Be Determined
FERC Pre-Filing PF26-7
Bakken East Pipeline Project
Gas Company: WBI Energy Transmission
350 miles of 36″ & 42″ from McKenzie Co. to Cass Co., ND
82 miles of 20″ in Barnes, Lamoure, & Dickey Co.’s, ND
9 miles of 8″ in Barnes Co., ND
Construction Start Date: Fall 2028
Contractor:
To Be Determined
FERC Pre-Filing PF26-4
Silver Spur Project
Gas Company: Northwest Pipeline (Williams)
88 miles of 24″
Elko Co., NV to Twin Falls Co., ID
Construction Start Date: Q4 2028
Contractor:
To Be Determined
FERC Pre-Filing: PF26-15
Sabine Crossing Pipeline
Gas Company: Sabine Pass Liquefaction/Cheniere Energy
55.6 miles of 48″
Liberty Co., TX to Cameron Parish, LA
Construction Start Date: 2029
Contractor:
To Be Determined
FERC Docket CP25-505
Bridge Project
Gas Company: Elba Express Company (Kinder Morgan
71 miles of 30″
Screven to Colleton Co., SC
Construction Start Date: Q1 2029
Contractor:
To Be Determined